Generation capacity
Enough to supply 40.000 people town
![](images/plant12.png)
Enviromental impact
Equivalent to 10.000 tree forest, saving more than 2.500 tonns of oil equivalent (TOE) import
![](images/plant15.png)
Electricity sale
Sale of electricity in the wholesale spanish electric market as a generator
Main assets
Below a selected list of some of some of our generation assets
-
Ábarán hydropower plant
Location: Abarán, Murcia, Spain
Opening year: 1.925
Segura river
2 turbine-generator groups
810 KW generation power
1 main building and 1 workshop
1 dam
310 meter long and 8,5x2,5 m2 section channel
24 m3/s watterflow
4,6 meter head -
Batanejos hydropower plant
Location: Villagordo del Júcar, Albacete, Spain
Opening year: 1.920
Júcar river
1 turbine-generator group
749 KW generation power
Main building and attached workshop
1 dam
400 meter lenght and 10x4 m2 section channel
14,57 m3/s waterflow -
Antoñana plant
Location: Antoñana, Alava
Operning year: 2.015
Collects water from Korres river
1 turbine-generator group
997KW generation power
Main building
2 Dam
8.500 meter lenght and 1,3x1,2 m2 section channel
1.350 meter penstock
1,5m3/s waterflow
76 meter head -
Gallipienzo hydropower plant
Location: Gallipienzo, Navarra, Spain
Opening year: 1.985 (original mill from 1687)
Aragón river
2 turbine-generator groups
1.400 KW generation power
Main building
1 Dam
50 meter lenght and 21x4 m2 section channel
40 m3/s waterflow
3,3 mts head -
Moranchel hydropower plant
Location: Jorquera, Albacete, Spain
Opening year: 1.943
Júcar river
2 trubine-generator groups
2.920 KW generation power
Mai building
1 dam
560 meter lenght and 8x3 m2 section channel
20 m3/s waterflow
13,78 meter head
-
Recueja hydropower plant
Location: Recueja, Albacete, Spain
Opening year: 1.921
Júcar river
2 turbine-generator groups
3440 KW generation power
1 Main building
1 Dam
2800 meter lenght and 8x3 m2 section channel
24 m3/s waterflow
11,74 meter head -
Solvente hydropower plant
Location: Solvente, Murcia, Spain
Operning year: 1.930
Segura river
2 turbine-generator groups
2940 KW generation power
1 main building
1 dam
756 meter lenght and 6x3 m2 section channel
25 m3/s waterflow
13,94 meter head -
Ulea hydropower plant
Loaction: Ulea, Murcia, Spain
Opening year: 1.959
Segura river
1 turbine-generator group
1600 KW generation power
1 main building
1 dam
1910 meter lenght and 4x3 m2 section channel
86 meter penstock
22 m3/s waterflow
9,4 mts head -
Yanci II hydropower plant
Location: Igantzi, Navarra, Spain
Operning year: 1.913
Latsa river
2 turbine-generator groups
560 KW generation power
1 main building
1 dam
5.500 meter length and 1,8x1,6 m2 section channel
350 meter penstock
1,2 m3/s waterflow
74 meter head -
Chirrisquin hydropower plant
Location: Valcarlos-Luzaide, Navarra, Spain
Opening year: 1.900
Collects water from Arnegui river
1 turbine-generator group
580 KW generation power
1 main building
680 meter lenght
6.850 meter penstock
0,5 m3/s waterflow
223 mts head